TEAM EXPERIENCE

UPS Fuel Farm Expansion

Louisville, Kentucky

This project for UPS consisted of concrete foundations and containment walls for two new 2,000,000 gallon fuel tanks and 25′ tall blast wall at the UPS Fuel Farm within the United Parcel Worldport Facility at Louisville International Airport. All work was performed during 24/7 operations that could not be interrupted at the Airport.

Project Data:

  • Construction Cost: $2,749,000
  • All work conducted adjacent to an Occupied Facility & Aviation Traffic
  • Completion: December 2017